Topic Last Modified: 2010-05-27

When you select the Transport Rules tab under Edge Transport, depending on whether the result pane shows a transport rule, the following actions are available either by right-clicking the transport rule or by using the action pane.

Change Priority

The Change Priority link is available only when you select a transport rule and you have more than one transport rules. It allows you to change the order in which transport rules are executed. For more details, see Organization Configuration > Hub Transport > Transport Rules > Change Priority.

Disable Rule

To disable the transport rule, click Disable Rule.

Enable Rule

To enable the transport rule, click Enable Rule.

Remove

Click Remove to remove the transport rule.

Edit Rule

Click Edit Rule to make changes to an existing transport rule by using the Edit Transport Rule wizard.

For More Information